Math, asked by workforpremrauniyar, 20 days ago

if 72 men can do a piece of work in 30 days, after 5 days how many days will 25 mens take to complete the work​

Answers

Answered by araimuskaan
1

Answer:

Men: Days:: Men: Days

72: 25 30: X

:. By inverse proportion

72 x 25 = 30 x x

25 × 72

30

= 60 days