If 72 workers can construct a road in 24 days, how many days will it take 36
workers to construct the same road
Answers
Answered by
1
Answer:
let days to complete the work be x
72 workers can construct a road in 24 days
36 workers can construct a road in x days
so,36x = 72× 24
x = 72× 24
36
x = 48
48 days