If 72 workers can do a piece of work in 40 days, in how many days will 64 workers complete the same work?

Answers

Answered by jahnavivooka
2

Answer:

45 days

Step-by-step explanation:

No. of workers = 72

Time taken = 40 days

Work done = 72 × 40

No. of workers = 64

Time taken = ?

Work done = 64 × x

64 \times x = 72 \times 40

x =  \frac{72 \times 40}{64}

= 45 days

Answered by sheeb12ansari
0

Given:  72workers can do a piece of work in 40days.

We have to find the number of days required to complete the same work by64 workers.

We are solving in the following way:

By using the concept of:

Total work = Number of men x Time taken

From the above problem, we can say that:

Total work done=72\times40

Time is taken by 64workers = \frac{72\times40}{64}

Solving the above equation further we get,

Time is taken by 64workers\Rightarrow 45

Hence, 45days will require to complete the same work by 64workers.