If 8 men can do a job in 12 days,how long will 24 men take to complete it?
Solve it by unitary method with solution!
Answers
Answered by
1
Answer:
4 days
Step-by-step explanation:
12 men takes 8 days
12×2=24 men takes 8/2=4 days
Answered by
1
Answer:
4 days will be required by 24 men
Step-by-step explanation:
8 men - 12 days
1 man - 12*8 days
24 men - (12*8) /24= 4