if 8 men can do a job in 12days how long will 24 men take to complete it

Answers

Answered by kshittu
1

Answer:

ans is 36

Step-by-step explanation:

24×12/8 as 8 men require 12 days then 24 men will require 36 days

Answered by ramanujan67
0

Answer:

36

Step-by-step explanation:

here's the answer....

hope it will be helpful for u...