if 8 men can do a job in 5 days ,how much time would 10 men take to do the same job?
Answers
Answered by
2
Answer:
Step-by-step explanation:
Men×days
8×5=x
=40
If 10 so
40/10
=4days
Answered by
1
Answer:
4 days
Step-by-step explanation:
8×5=40 = step 1
40÷10=4days =step 2
MARK ME AS BRAINLIEST