Math, asked by aminasania, 1 year ago

if 8 men can do a piece of work in 10 days,how long will 10 men take to do the same work?

Answers

Answered by sahilnagda19
2
12.5 days will take 10 men to do the work

Hope this Helps And is Right
Answered by SPYBOY8
1
10/8=1.25
so 10×1.25=12.5
12.5 is the answer