If 8 men can do a piece of work in 15
days, then in how many days could 20
men do the same work
Answers
Answered by
9
Heya mate,Here is ur answer
8 men=15 days
1 men=120 days
As when men will decrease,days will increse
20 men=?
2
So, 20 men will complete the work in 6 days.
Warm regards
@Laughterqueen
Be Brainly ✌✌✌
8 men=15 days
1 men=120 days
As when men will decrease,days will increse
20 men=?
2
So, 20 men will complete the work in 6 days.