Math, asked by alanvallikunneljoy, 3 months ago

If 8 men can do a piece of work in 20 days, in how many days could 20 men do the same work?​

Answers

Answered by panesarh890
5

Answer:

Chakmi,

Thanks for A2A.

We will approach this question by using unity method

8 men can do a piece of work in 15 days

1 man can do a piece of work in 15*8 days

20 men can do a piece of work in 15*8/20 days = 6 days

20 men do the same work in 6 days

Cheers

Answered by Ves1857
4

refer attachment for your answer

Attachments:
Similar questions