if 8 men can du a job in 5 days how much time would 10 mens to du the same job ​

Answers

Answered by Sanju1534
5

Answer:

Time taken by 8 men to do a job = 5 days

Time taken by 1 man to do a job = 5/8

Time taken by 10 men to do a job = 5 × 10

__

8

= 25/4

= 6.25 days

Ans. 6.25 days

Hope it helps.

Answered by annaanil965
0

Answer:

8*5=10*x

- x=40/10=4

Step-by-step explanation: