If 8 men or 12 women can do a piece of work in 10 days, then the number of days required by 4 men and 4 women to finish the work is
Answers
Answered by
1
Answer is 12 days
mark the ques brainliest if you agree
Attachments:
Answered by
0
The number of days required by 4 men and 4 women to finish the work is 12 days.
Step-by-step explanation:
Since we have given that
8 men or 12 women can do a piece of work = 10 days
Number of days for 4 men and 4 women is given by
Hence, the number of days required by 4 men and 4 women to finish the work is 12 days.