if 8 person working 8 hours a day can complete a work in 15 days then how many person can complete a work in 6 days by working 10 hours a day
Answers
Answered by
2
Answer:
16 Persons
Step-by-step explanation:
Work Complete is
Hours x persons x days
if,
8 x 8 x 15 = 960
Now Number of Persons are
960 = 10 x persons x 6
persons = 960/60
persons = 16