Math, asked by aayushisharma0612199, 2 months ago

if 8 person working 8 hours a day can complete a work in 15 days then how many person can complete a work in 6 days by working 10 hours a day​

Answers

Answered by ta3951
2

Answer:

16 Persons

Step-by-step explanation:

Work Complete is

Hours x persons x days

if,

8 x 8 x 15 = 960

Now Number of Persons are

960 = 10 x persons x 6

persons = 960/60

persons = 16