Math, asked by msaditi2108, 2 months ago

If 8 workers can build a road in 6 days, how many days will 3
workers take to build the same road?
1 =
plz tell ​

Answers

Answered by prasanthikuchipudi
1

Answer:

16 days

Step-by-step explanation:

we know,

work=men*hours*days

given,

if 8 workers can build a road in 6 days

1 work=8 workers* 6 days

how many days will 3 workers will take to build the same road

let x be the days

1 work=3 workers* x days

if work is same then,

8 workers*6 days=3 workers* x days

x=16 days