If 8 workers take 12 days to complete one task, how many days will 6 workers take to complete the same task? ( tell me fast and if u have done or don't know solve my other question)
Answers
Answered by
2
Answer:
8 workers = 12 days
1 workers= 12×8= 96 days
6 workers= 96/6= 1 6 days
mark me brainliest or I will never answer questions
Answered by
1
SOLUTION
- 8 workers takes 12 days
- let 6 workers can do in x days.
- If no. of worker decreases then working days will increases.
- This is inversely proportional