If 9 men can repair a road in 12 days ,how many days will 27 men take to complete the same work ?
a.4 b.6 c.19 d.18
Answers
Answered by
1
Answer:
a. 4
Step-by-step explanation:
Time taken to repair road by 9 men = 12 days
Time will taken by 1 to repair road = 9 x 12 = 108 days
So, The time will taken by 27 men to repair road = 27/108= 4 days
if like it so, mark it as brainiest
Answered by
13
Answer:
4 is your answer dude .......hope it helps u