Math, asked by simranclair0101, 3 months ago

if a 4 men or 8 women can finsih a work in 10 days how long will 6 men and 8 women take to finish da same work​

Answers

Answered by spratimabala
0

Answer:

10000000000000

Step-by-step explanation:

Answered by OppaiSugoy
0

Answer:

4 days

Step-by-step explanation:

4 men OR 8 women finish work in 10 days

i.e 1 men's work = 2 women's work

So we can say 8 women = 4 men = 10 days

Therefore

6 men + 8 women = 6 men + 4 men = 10 men

4 men's per day work = 1/10

1 man's per day work = 1/40

So 10 men's per day work = 10x 1/40 = 10/40 = 1/4

So day's reqd by 10 men to complete the task = 1/(1/4)

= 4 days

Similar questions