Math, asked by rohitsingh7026, 7 months ago

If A & B can do a job in 8 days and B & C can do the same job in 12 days. If A, B & C work together they can finish the job in 6 days. In how many days can A & C finish the job?

Answers

Answered by hs26102005
2

Answer:

8 days

Step-by-step explanation:

Using LCM method:

total work is equal to LCM of 8, 12 & 6 i.e. 24 units

A+B=8 Days; B+C=12 Days; A+B+C=6 Days.

So, A+B complete 3 parts per day. (24/8=3)

B+C complete 2 parts per day.(24/12=2)

A+B+C complete 4 parts per day. (24/6=4)

Now, 2(A+B+C)−(A+B)−(B+C)=(A+C)

=>(A+C)=2*(4)−3−2

=>(A+C)=3 parts per day.

A & C will take 8 days to complete.(24/3=8)

Hope it helps you