Math, asked by basantaukn, 18 hours ago

If A and B can complete a piece of work in 6 and 8 days respectively by working 7 hrs per day. In how many days they can complete the work by working together 8 hrs per day?​

Answers

Answered by rc3165077
0

Answer:

hii and the rest of the input are not the

Answered by goutamsinha2012
1

If two persons A and B works 7 hours a day, then A and B alone can complete a piece of work in 6 days and 8 days respectively. While working 8 hours a day, in what time they would complete it together? A alone can complete the work in 42 days working 1 hour daily. Similiarly, B will take 56 days working 1 hour daily.