If A and B can do a piece of work in 8 days. B and C can do in 12 days. A and C can do in 8 days. Then, A, B and C altogether can complete the same work in how many days? ​

Answers

Answered by Antara30
0

Answer:

A, B and C can do a given piece of work in 6 days. Hence, A and C together complete the work in 8 day. Similary it is 48/12 = 4 work for B & C and 48/6 = 8 work for A & B & C together.