Math, asked by yaduvedra3124, 5 months ago

If A and B can finish a task in 42 days provided the ratio of efficiency between A and B is 7:3, then how many days will A take to complete the task alone?

Answers

Answered by dandi19
3
Let A be the number of days it will take A to complete the task alone.

Then, since the ratio of efficiency of A and B is 7:3

Solution:

Let the task be considered to have
42 * 10 = 420 of work.

In one day both A and B can do = 42/10 = 4.2

In one day A can do 7 units and B can do 3 units.

The number of days required by A to complete the task alone= 420/7 = 60

Therefore, A will take 60 days to complete the task alone.

Hope this will help.