If A and B complete a work in 4 days while alone take 12 days. In how many days will B alone complete that work.
Answers
Answered by
0
Answer:
6 days
Step-by-step explanation:
A can complete work in 12 days alone
both A & B in 4 days
Creating an equation for 1 day work by A & B
A=1/12
B=1/x
A+B = Total work
1/12 + 1/x = 1/4
Solving for x
x = 1/6
hence 6 days