If A and B together finish a work in 15
days and B alone finish this work in 20
days, then in how many days will A alone
finish the work?
(a) 60 (b) 63
(c) 75 (d) 15
Answers
Answered by
11
Answer:-
Number of days A will take to finish the work
• Given:-
A and B together finish a work in 15 days.
B alone finishes the work in 20 days.
• To Find:-
Time taken by A to finish the work alone.
• Solution:-
✧ Time taken by A+B to complete the work = 15 days
Work of A+B in 1 day = 1/15
✧ Time taken by B to complete the work = 20 days
Work of B in 1 day = 1/20
✧ Time taken by A to complete the work = Time taken by [A+B] - Time taken by B
→
Taking LCM:-
→
→
Therefore, A will have to work for 60 days to finish the work.
Answered by
8
Answer :-
- A → 60
Given :-
- A and B together finish a work in 15 days and B alone finish this work in 10 days
To Find :-
- In how many days will A alone finish this work ?
Solution :-
• Time taken by A + B to complete the work → 15 days
→ Work of A + B in one day → 1/15
• Time taken by B to complete the work → 20 days
→ Work of B in one day → 1/20
★ Time taken by A to complete the work = Time taken by A + B - Time taken by B
→ 1/15 - 1/20
→ 4 - 3/ 60
→ 1/60
Hence, A will take 60 days to complete the work alone.
Therefore option [A] is correct.
Similar questions