if A can complete a work in 10 days and B can complete the same work in 12 days individually, then how many days will the work get completed if the work simultaneously.
Answers
Answer:
In days ,the work get completed if the work simultaneously.
Step-by-step explanation:
Given,
A can complete a work in 10 days.
A can complete work in one day=
B can complete the same work in 12 days
B can complete work in one day=
A and B will do work in a day=
L.C.M between 10 and 12 is 60
So together they can complete work in days.
Step-by-step explanation:
Given,
A can complete a work in 10 days.
A can complete work in one day=\frac{1}{10} work
10
1
work
B can complete the same work in 12 days
B can complete work in one day=\frac{1}{12} work
12
1
work
A and B will do work in a day=
\frac{1}{10}+\frac{1}{12}
10
1
+
12
1
L.C.M between 10 and 12 is 60
\begin{gathered}=\frac{6+5}{60} \\ \\ =\frac{11}{60}\end{gathered}
=
60
6+5
=
60
11