Math, asked by shaikyasin8097, 8 months ago

If A can complete a work in 16 days then in how many days can be complete 3/4 of the work

Answers

Answered by chikodesmitesh
1

Answer:

12 days

Step-by-step explanation:

If a man takes 16 days to complete his full work, then he completes 1/4th of his work in every 4 days. Hence, he completes 3/4th of his work in - 4*3=12 days.

Similar questions