If A can do a piece of work in “n” days then work done by A in one day=??
Answers
Answered by
0
Answer:
work done by A in one day=1/n
Step-by-step explanation:
Time taken by A to do a piece of work = n days
Amount of work done by A in n days = 1
Amount of work done by A in 1 day = 1/n