If A can finish a work in n days then part of work finished in 1 day is *
1-n
n-1
none
1/n
Answers
Answered by
7
Answer:
1-n is the answer
Step-by-step explanation:
Mark me brainliest
Answered by
12
We are given that : 'A'can finish a work in 'n' days.
i.e. The number of days taken by A to complete the whole job = n
Let we denote the whole work done by 1.
Then, the part of work finished in 1 day would be
Hence, If 'A'can finish a work in n days, then part of work finished in 1 day is
Similar questions