Math, asked by manish375abc, 10 months ago

if A complete a work in 15min and B complete a work in 45 minute then how much time they take if they work together?​

Answers

Answered by Anonymous
2

Answer:

A completes a job in 20 minutes and B does so in 30 minutes. If they do the same job together, how much time they will take?

What’s beauty inside and out for Elsa Pataky? Know more!

We want to know how long they will take to actually get the FULL job done.

Step 1: Turn them into fractions. We need to convert the amount of time “A” takes and “B” takes to the simplest form possible. “A” will complete 1/20 of the job in one minute. “B” will complete 1/30 of the job in a minute.

Step 2: Adding the fractions. Now, we add 1/20 and 1/30 together. 1/20 plus 1/30 is equal to 3/60 plus 2/60 which gives us the answer of 5/60. If the pay work together, they will accomplish 5/60 of the job in a minute. Now, this is ONLY 5/60. We want to know the amount of time they take to get the FULL job done.

Step 3. Divide 60 by 5. Sixty divided by five is equal to 12.

As a result, team “A” and team “B” take 12 minutes to get the job done if they work together.

ANSWER : 12 MINUTES.