Math, asked by jakeleigh007, 6 days ago

If a contractor agreed to finish a given work in 75 days. He puts 160 man who works 9 hrs a day. After 55 day he finds only 1/3 work is completed. How many more persons should engage to complete the work in time if now they work 10 hrs a day.

With proper solution Please.​

Answers

Answered by vinayak8257
0

Answer is in the attachment please mark me as brainlists and follow me

Attachments:
Similar questions