Math, asked by peterrajantr, 9 months ago

If A does a work in 35 days and B's capacity to do work is 40% more than b . Then in how much days will B complete his work

Answers

Answered by MagicalGiggles
4

<body bgcolor=b>

\huge\mathbb\pink{DULARI..!!}

<font color = white>

Let the total work = 100 units

A can complete 100 units in 35 days

B is 40% more efficient

he can complete = 140 unit in 35 days

B can complete 100 units in

35 / 140 × 100

25

B can complete his work in 25 days .

<marquee>♓DULARI♓</marquee>

Similar questions