If a man takes 15 days to complete a piece of work, what part of the work will 2 men complete in 5 days?
Answers
Answered by
1
Answer:
1 man takes 15 days
2 man will take half i.e 7.5 days
the work of 2.5 days will be left
Answered by
5
Answer:
2/3 rd work
Step-by-step explanation:
Since , a man takes 15 days to complete a piece of work
∴ Total work the man will do will be =
= 15 work
∴ The total work is 15
Now , we have to find part of the work completed by 2 men in 5 days
∴ The two men in 5 days will complete work respectively.
= 10
Now, the part of work completed be 2 men in 5 days as compared to total will be th of total work
= of total work