Math, asked by harrisonshika12, 4 months ago

if a worker is given 960 for 12 days how much is he given in 10 days​

Answers

Answered by sg70sahil
2

given: worker is given 960 for 12 days

960÷12

80

so we know that worker is given 80 for 1 day

therefore gor 10 days

10×80

800

Answered by TrueRider
63

Work done by A in 1 day =1/9

Work done by B in 1 day = 1/18

Work done by B in last 3 days = 1/18×3= 1/6

Remaining work=1−1/6= 5/6

Work done by A and B in 1 day = 1/9+ 1/18= 3/18= 1/6

Hence no. of days in which A and B worked together is =5/6|1/6 =5 days

Then total time to complete the work =3+5=8 days.

Same like this process you have to do

Similar questions