Math, asked by gxbxdj, 11 months ago

If A works alone, he would take 4 days more to complete the job than if both A and B worked together. If B worked alone, he would take 16 days more to complete the job than if A and B work together. How many days would they take to complete the work if both of them worked together?​

Answers

Answered by pragyakirti12345
2

Answer: 8 days

Step-by-step explanation:

Let the work completed by both A and B together be x.

∴ (x + 4) days will be required to complete the work done by A alone.

∴ (x + 16) days will be required to complete the work done by B alone.

According to the question:

If both work together, work will be completed in x days.

\frac{1}{x + 4}  + \frac{1}{x + 16} = \frac{1}{x}

\frac{x + 16 + x + 4}{(x + 4) (x + 16)}  = \frac{1}{x}

\frac{2x + 20}{x^{2} + 20x + 64}  = \frac{1}{x}

2x^{2}  + 20x = x^{2}  + 20x + 64

x^{2}  = 64

∴ x = 8 days

∴ 8 days will be required to complete the work , if both A and B works together.

Answered by bharathparasad577
0

Answer:

Step-by-step explanation:

Given:

Working together, A and B do the job in x days

A does the job in x + 4 days. A completes \frac{1}{x + 4} of the job per day

B does the job in x + 16 days. B completes \frac{1}{x + 16 } of the job per day

To Find:

We need to find the number of days would take if both of them worked together

Solution:

\frac{1}{x+4} + \frac{1}{1+16} = \frac{1}{x}

\frac{(x+16)+(x+4)}{(x+4)(x+16)}=\frac{1}{x}

\frac{x+16+x+4}{(x+16)(x+4)}=\frac{1}{x}

x (2x + 20) = (x + 4) (x + 16)

2x^{2}  + 20x = x^{2}  + 20x + 64\\x^{2}  = 64\\x  = \sqrt{64} \\x = +8, -8

-8 is an extraneous solution, so x = 8

If A and B are worked together, it would take 8 days to completes the job.

#SPJ2

Similar questions