If four persons can finish an assignment in 15 days. How many persons will be required to finish the same assignment in 20 days?
Full solution
Answers
Answered by
0
Answer:
Let the amount of work be W
If a person finishes the work in 15 days
Then amount of work in 1 day by 1 person = W/15
Amount of work done by 3 person per day = 3*W/15 = W/5
So total days to be taken by 3 persons = W/(W/5)
= 5 days
Answered by
0
Answer:
it's the question of inverse proportion means if number of persons increases the days decreases
means a×b=c×d
15×4=x×20
x=3 days