if hemanth works for 20 days and manoj, work for 15 days then 3/5th work has been completed. if manoj works for 60 days and hemanth works for 16 days then 2/5 of the work has been completed. find in how many days both can completed the work together
Answers
Both can completed the work together in "30 days".
Step-by-step explanation:
Let efficiency of Hemant = h units/day and
Efficiency of Hemant = m units/day
According to question,
=
⇒ 40 h + 30 m = 18 m + 48 h
⇒ 30 m - 18 m = 48 h - 40 h
⇒ 12 m = 8 h
∴ =
Let h = 3x and m = 2x
∴ Total work = × 5 = 150x
∴ Required time = = 30 days
Hence, both can completed the work together in 30 days.
Both the Hemanth and Manoj can completed the work together for 30 days.
Given:
If hemanth works for 20 days and manoj, work for 15 days then 3/5th work has been completed.
If manoj works for 60 days and hemanth works for 16 days then 2/5 of the work has been completed.
To find:
Find in how many days both can completed the work together
Solution:
Let the efficiency of hemanth be 'a' and manoj be 'b'
Therefore,
Dividing there equations, we get
40a + 30b = 48a + 18b
8a = 12b
let a = 3x, b = 2x
Total work =
Time required = = 30 days
Result:
Both the Hemanth and Manoj can completed the work together for 30 days.
To know more:
Mohan takes 16 days less than manoj to do a piece of work . Both working together will finish it in 15 days .How many days will manoj alone take to finish the work
https://brainly.in/question/4098203