if it takes 3 hours for 8 workers to paint a fence how long will it take 6 workers
Answers
Answered by
5
Answer:
The time taken and number of workers are in inverse variation.
Step-by-step explanation:
Time taken by 8 workers = 3 hours
Time taken by 1 worker = 8×3 hours
Time taken by 6 workers = 8×3/6 hours = 4 hours