. If it takes 4 people 4 days to dig a
hole, how long does it take 2 people
to dig a half hole ? ​

Answers

Answered by anushka54189
2

Answer:

Two days.

It's obvious.

Please mark as brainliest.

Answered by Mp5killer
4

Answer:

The total input required to dig the original hole is 4 people x 4 days, so 16 man-days. Half that input is 8 man-days. Divide that by the 2 people digging, and you get 4 days...