Math, asked by diyarawat625, 1 month ago

If it takes 40 days for 120 men to complete a work, how long will it take for 80 men to complete the same work​

Answers

Answered by vashunehra05
3

Answer:

240

Step-by-step explanation:

120 men takes= 40 days

1 man will take= 120/40 days =3 days

80 men will take = 3*80 days

                            = 240 days