If it took 5 boys 45minutes to finish a piece of work, how long would 9 boys finsh the same work?
Attachments:
Answers
Answered by
0
Answer:
answer
Step-by-step explanation:
fozjkzrivstkvv rg b vt of g
Answered by
1
Step-by-step explanation:
5 boys =45 mins
1 boy=45/5mins
that is, it would take 1 boy 9 mins to complete the
work
time taken by 9 boys:
9 boys =9×9 mins
9 boys = 81 mins to complete the work
hope it helps you please mark me as brainliest