If man A complete a piece of work in 12 days and
the same work is completed by B and C in 15 days
and 20 days respectively. In how many days the
work is completed if they work together?
(A) 4 days (B) 8 days
(C) 5 days (D) 6 days
Answers
They work together :
- A complete a piece of work in 12 days
- B complete a piece of work in 15 days
- C complete a piece of work in 20 days
First we take LCM of these numbers 12 , 15 , 20
so, LCM is 60 ( total work is 60 )
A complete whole work in 12 days and total work is 60
then A complete work in 1 day = 60/12 = 5 (efficiency of A )
B complete whole work in 15 days and total work is 60
then B complete work in 1 day = 60/15 = 4 (efficiency of B )
C complete whole work in 20 days and total work is 60
then C complete work in 1 day = 60/20 = 3 (efficiency of C )
now in 1 day A , B and C together complete work = 5 + 4 + 3 = 12
so , total work = 60
A + B + C = 60/12 = 5 day
so, option C is correct .
Know more
Q.1.- If a can complete a piece of work in 15 days and B can complete the same work in 12 days how many days will both of them take to complete the work
Click here- https://brainly.in/question/7558054
Q.2.- A and b can complete a work in 12 days together, b and c can complete the same work in 15 days together and a and c can complete that work in 20 days together. in how many days a can complete the same work alone?
Click here- https://brainly.in/question/1744674
Q.3.- A and b can do a piece of work in 6days b and c in 8days a and c in 12days if they work together and a leaves after 4days how many days remaining b and c complete
Click here- https://brainly.in/question/9044993