If nine women can sew 375 dresses in 8 weeks, calculate the time it would take four women to perform the same task? Inverse

Answers

Answered by riddhirajbhattacharj
5

Answer: 18 weeks

Step-by-step explanation:

Time taken by 9 women to sew 375 dresses = 8 weeks

Time taken by 1 women to sew 375 dresses = 9 x 8 weeks

                                                                            = 72 weeks

Time taken by four women to sew 375 dresses = 72/4 weeks

                                                                                  = 18 weeks