If one boy complete a work in 1 day then in how may days 2 boys will complete this work
Answers
Answered by
0
Answer:
I think two days . but why you have to get the completed by the boys as it is already completed
Answered by
0
Answer:
1/2days
as 1 boy does x amt of work in 1 day .
So 2 boys will do 2x work in one day.
Hene they will take 1/2 day to complete the work