If Ram and Raman can do a job in 12 days and 18 days, respectively .How many days would they take to complete the job altogether?
Answers
Answered by
10
Answer:
8
Step-by-step explanation:
Work done by Ram in one day = 1/12
Work done by Raman in one day = 1/18
Work done by them together in one day = 1/12+1/18 = 5/36
Therefore days taken to complete the work
= 36/5 = 7.2 = 8 days (round off to next day)