If ritam takes 50% more time than sohan to do a work and if they together do the work in 18 days then find how much time shall ritam take to do the work

Answers

Answered by siddarthadiga
0

Answer:

9

Step-by-step explanation:

Answered by Vikramjeeth
3

*Question:

✍️✍️✍️✍️✍️✍️✍️

If ritam takes 50% more time than sohan to do a work and if they together do the work in 18 days then find how much time shall ritam take to do the work .

*Answer:

✍️✍️✍️✍️✍️✍️

Let we take Ritam as "a" and

Let we take Sohan as "b" .

Ratio of time

=> a : b

=> 2 : 3

( \frac{a}{b} =  \frac{150\%}{100\%}  =  \frac{3}{2} ) \\

efficiency of work = 2 : 3 (Efficiency is always is always proportion to time ).

Total work = 18 days × ( 2 + 3 ) unit.

= 90 units .

a completes work in

 =  \frac{90units}{3 \: units \: per \: day \: }  \\   \\  =  \: 30 \: days \:  \:  \:  \:  \:  \:  \:  \:  \:  \:  \:  \:  \:  \:  \:  \:

So the Ritam will take 30 days to do the work .

☑️☑️