If Rs.12000 paid for 15 workers for 20 days, how much would it need to pay for
5 workers for 12 days?
Answers
Answered by
1
Answer:
Rs 4000
Step-by-step explanation:
15 workers for 20 days = Rs 12000
1 worker for 20 days = Rs 12000/15 = Rs 800
1 worker for 1 day = Rs 800/12 = Rs 200/3
5 workers for 1 day = Rs 200/3 × 5
5 workers for 12 days = Rs 200/3 × 5 × 12 = Rs 4000