If Shubham is 3 times as efficient as Rahul and Rahul is 50% as efficient as Arun and hence Shubham completes a work 15 day less than the number of days taken by Arun. If Shubham, Rahul, and Arun all work together then in how many days can they complete the work?
Answers
Answered by
0
Answer:
yrr unko kaam krna de yrr
Step-by-step explanation:
please mark me brainlist;););)
Answered by
0
Answer:
GIVEN :
A can complete the work in 36 days and B can complete the same work in 45 days.
C’s work efficiency is 20% of the work efficiency of A.
CALCULATION :
Let, A’s efficiency = x/day
∴ C’s efficiency = x × 20/100 = 0.2x/day
Let, C can complete the work in a days
According to problem,
⇒ x × 36 = 0.2x × a
⇒ a = 36/0.2
⇒ a = 180
∴ C can complete the work in 180 days
Let, they together can complete the work in = y days
According to problem,
⇒ y (1/36 + 1/45 + 1/180) = 1
⇒ y ((5 + 4 + 1)/180) = 1
⇒ y = 180/10
⇒ y = 18
∴ A, B and C together can complete the work in = 18 days