If sonu works 10 hours per day, he can finish a job in 28 days. If he has to finish the job in 20 days. How many hours should he work per day?

Answers

Answered by nishasingh28300
2

Answer:

Step-by-step explanation:

As 28 days work=10HR

FOR 1 DAY=10×28=280

FOR 20 DAYS=280/20=14