Math, asked by govindm900010, 11 hours ago

if team a & team b together can complete a piece of work in 15 days where has B alone can do with in 20 days how many days a takes to do work alone please give me a full solution​

Answers

Answered by BRAINLY1OFFICIAL
0

Answer:

A alone will do the work in 60 days.