Math, asked by archishagamare, 7 months ago

If the person takes 3 hours to complete 5 dresses, how many dresses are made per hour?

Answers

Answered by lillianmadden
3

Answer:

Adam can finish the work in 15 days.

Therefore, Adam’s 1 day’s work = 1/15

Brandon can finish the work in 10 days.

Therefore, Brandon’s 1 day’s work = 1/10

So, (Adam + Brandon)‘s 1 day’s work = 1/15 + 1/10 = (2 + 3)/30 = 5/30 = 1/6

Therefore, (Adam + Brandon)‘s 5 day’s work = 5 × 1/6 = 5/6

Remaining work = 1 – 5/6 = 6-5/6 = 1/6

This remaining work has to be done by Brandon.

Complete work is done by Brandon in 10 days.

Therefore, 1/6 of the work is done by Brandon in (10 × 1/6) days = 5/3 days.

Hence, the remaining work is done by Brandon in 5/3 days.

Step-by-step explanation:

Similar questions