If the ratio of the work done by (x + 2)
workers in (x-3) days to the work
done by (x + 4) workers in (x-2) days
is 3:4, then what is the value of x?
(a) 8
(b) 10
(c) 12
(d) 13
Answers
Answered by
2
Correct answer is Option c..
Answered by
0
Answer:
the option c is the answer
I hope it helps you