If the total on-cost for a milling machine for the year 2010-2011 is Rs.10000 and the machine works for 2500 hours in a year, calculate the on-cost allocated to the product using 3/2 machine-hours b machine hour rate method?
Options:
a) rs 2
b) rs 4
C) rs 8
D) rs 6
Answers
Answered by
1
Answer:
D. rs6
Step-by-step explanation: